Building Your Indoor Farm

Building an indoor farm is a significant investment that requires careful planning and consideration. One of the key factors to take into account is the timeline of construction, which can vary depending on the type of structure you choose. When comparing modular structures and traditional bricks and mortar farms, it's essential to consider the time it takes to build each option.

Modular Farm Timeline:

A modular farm can be a much quicker option, with an estimated construction timeline of 6-9 months. Here's a breakdown of the modular farm timeline:

Month 1-2: Design and Planning

During the first phase of construction, you'll work with a modular manufacturer to design a structure that meets your needs. This process usually takes around 1-2 months.

Month 3-5: Factory Production and Site Preparation

While the modular manufacturer produces the individual sections of your farm in their factory, you can begin preparing the site for installation. This includes pouring a foundation and ensuring the site is level and ready for the modular sections to be installed. This phase typically takes 2-3 months.

Month 6-7: Installation

Once the modular sections are complete, they are transported to your site and installed. This process usually takes around 1-2 months, depending on the size and complexity of the structure.

Month 8-9: Finishing Touches

With the structure installed, you can begin adding finishing touches like lighting, HVAC systems, and other necessary components. This phase typically takes around 1-2 months.

Total Timeline: 6-9 months

Bricks and Mortar Farm Timeline:

In comparison, a traditional bricks and mortar farm can take much longer to build, with an estimated timeline of 18-24 months. Here's a breakdown of the bricks and mortar farm timeline:

Month 1-2: Design and Planning

During the first phase of construction, you'll work with an architect and designer to create a design that meets your specific needs. This process usually takes around 1-2 months.

Month 3-6: Permitting and Approvals

Once the design is finalized, you'll need to obtain the necessary permits and approvals from local authorities. This process can take anywhere from a few months to half a year, depending on your location and the complexity of your project.

Month 7-22: Construction

The actual construction process for a bricks and mortar farm can take anywhere from several months to a year or more, depending on the size and complexity of the structure.

Month 23-24: Finishing Touches

With the structure built, you can begin adding finishing touches like lighting, HVAC systems, and other necessary components. This phase usually takes around 1-2 months.

Total Timeline: 18-24 months

As you can see, there's a significant difference in the time it takes to build a modular farm versus a bricks and mortar farm. While the exact timeline will depend on the size and complexity of your project, a modular farm can be completed in 6-9 months, while a traditional bricks and mortar farm can take 18-24 months or more. If you're looking for a faster, more efficient way to build your indoor farm, modular may be the best option for you.